Commercial Court clears up JCT80
Language: English Series: Building ; 258(7786) 19 March 1993, 32(1)Publication details: 1993Subject(s): Summary: Discusses the case "McAlpine Humberoak v McDermott International" (Abs43763) which held that extensions of time for relevant events occurring when the contractor is in default are to be backdated.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS48148 (Browse shelf(Opens below)) | 1 | Available | 65227-1001 |
Discusses the case "McAlpine Humberoak v McDermott International" (Abs43763) which held that extensions of time for relevant events occurring when the contractor is in default are to be backdated.