Language: English Series: Building ; 250(23) 6 June 1986, 49-50(2)Publication details: 1986Subject(s): Summary: In the construction of London Bridge City the construction management system has allowed the fitting out works to be incorporated in the original shell and core building programme, saving approximately 11 months on the overall project timetable.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS36400 (Browse shelf(Opens below)) | 1 | Available | 77717-1001 |
In the construction of London Bridge City the construction management system has allowed the fitting out works to be incorporated in the original shell and core building programme, saving approximately 11 months on the overall project timetable.