Claims between sub and main contractor
Series: Contract Journal ; 401(6252) 17 November 1999, 25(1)Publication details: 1999Subject(s): Summary: Uses the case "Ascon v Alfred McAlpine" to illustrate the problems which can arise in delay claims between the main contractor and subcontractors.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS61476 (Browse shelf(Opens below)) | 1 | Available | 102319-1001 |
Uses the case "Ascon v Alfred McAlpine" to illustrate the problems which can arise in delay claims between the main contractor and subcontractors.