Image from Google Jackets

Discain Project Services Ltd v Opecprime Developments Ltd

Series: Construction Industry Law Letter ; [2001] CILL 1739-1741(3)Publication details: 2001Subject(s): Online resources: Summary: TCC 11 April 2001. An application for summary judgment was refused on the grounds that to enforce the adjudicator's decision as, whilst it was accepted that was no actual bias on the his part, the adjudicator had failed to control the conduct of the proceedings as to prevent him being improperly approached by one of the parties and that this constituted a substantial breach of the rules of natural justice. Copy of judgement available on http://porch.ccta.gov.uk/courtser/judgements.nsf/Search/EF755F9F752FDE1F80256A34005BC423?OpenDocument
Holdings
Item type Current library Call number Copy number Status Barcode
Law report London Journal article ABS64142 (Browse shelf(Opens below)) 1 Available 113456-1001

TCC 11 April 2001. An application for summary judgment was refused on the grounds that to enforce the adjudicator's decision as, whilst it was accepted that was no actual bias on the his part, the adjudicator had failed to control the conduct of the proceedings as to prevent him being improperly approached by one of the parties and that this constituted a substantial breach of the rules of natural justice. Copy of judgement available on http://porch.ccta.gov.uk/courtser/judgements.nsf/Search/EF755F9F752FDE1F80256A34005BC423?OpenDocument