Discain Project Services Ltd v Opecprime Developments Ltd
Series: Construction Industry Law Letter ; [2001] CILL 1739-1741(3)Publication details: 2001Subject(s):- MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
- MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION-ADJUDICATORS
- BIAS
- COMMUNICATION
- DISCAIN PROJECT SERVICES LTD V OPECPRIME DEVELOPMENT LTD
- IMPARTIALITY
- NATURAL JUSTICE
- TELEPHONES
- MANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION
| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Law report | London Journal article | ABS64142 (Browse shelf(Opens below)) | 1 | Available | 113456-1001 |
TCC 11 April 2001. An application for summary judgment was refused on the grounds that to enforce the adjudicator's decision as, whilst it was accepted that was no actual bias on the his part, the adjudicator had failed to control the conduct of the proceedings as to prevent him being improperly approached by one of the parties and that this constituted a substantial breach of the rules of natural justice. Copy of judgement available on http://porch.ccta.gov.uk/courtser/judgements.nsf/Search/EF755F9F752FDE1F80256A34005BC423?OpenDocument