In the dock: vague clauses and reluctant adjudicators
Series: Construction News ; (6843) 20 November 2003, 16(1)Publication details: 2003Subject(s):- HOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
- THOMAS-FREDRIC'S (CONSTRUCTION) LTD V WILSON
- ST ANDREWS BAY DEVELOPMENT LTD V H B G MANAGEMENT LTD
- MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
- BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
- MANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION
| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS67428 (Browse shelf(Opens below)) | 1 | Available | 125085-1001 |
In "Thomas-Fredric's (Construction) Ltd v Keith Wilson" ([2003] EWCA Civ 1494, [2004] BLR 23-30(8) the case centred on whether or not the contract was evidenced in writing, as required by the Housing Grants, Construction and Regeneration Act 1996. A contract had been entered into with Thomas-Fredric (T-F) for the construction of two dwellings on land at the rear of Keith Wilson's home (K). The agreement was terminated and a second agreement entered into for completion of the work. The second gave rise to a dispute. It was made orally and was evidenced by a letter from the developer's surveyor to T-F, which stated that further payments would be made on condition that the value of the work is carried out diligently and that the value of the works is considered correct to that amount. K countersigned this, on behalf of Gowersand Ltd. Later dispute hinged on this, as it highlighted lack of clarity in correspondence. Article also examines issue of time limit for decisions, as highlighted in "St Andrews Bay Development Ltd v H B G Management Ltd" ([2003] CILL 2016, Abs66798).