Glauser International SA v Khan t/a Khan Design Consultants

Glauser International SA v Khan t/a Khan Design Consultants - 2002 - Building Law Reports [2002] 5 BLR 224-335(12) .

CA 25 March 2002. G appealed against earlier rulings to strike out two claims for damages for defective work and delays on the grounds of procedural non-compliance. "Held" the appeals were allowed on the grounds that the striking out of the first claim without giving a short extension of time was wholly disproportionate and wrong as it was not one to strike out with the intention of precluding a second claim. Full copy of judgement available on the Court Service website http://www.courtservice.gov.uk/View.do?id=1116&searchTerm=Glauser&ascending=false&index=0&maxIndex=0.