Claims explained
Knowles, R.
Claims explained - 1988 - Chartered Quantity Surveyor 10(10) June 1988, 9(1) .
Discusses the unreported decision in Whittal Builders Co v Chester-le-Street District Council (1985), which concerned evaluation of the contractor`s claim . The contract with the local authority provided for the contractor to refurbish a number of houses. The dispute arose due to the late handover of the dwellings to the contractor.
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
COMPENSATION
DELAY
OVERHEADS
PROFIT
Claims explained - 1988 - Chartered Quantity Surveyor 10(10) June 1988, 9(1) .
Discusses the unreported decision in Whittal Builders Co v Chester-le-Street District Council (1985), which concerned evaluation of the contractor`s claim . The contract with the local authority provided for the contractor to refurbish a number of houses. The dispute arose due to the late handover of the dwellings to the contractor.
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
COMPENSATION
DELAY
OVERHEADS
PROFIT