Risk factors leading to cost over-run in highway projects [electronic resource]

Creedy, Garry

Risk factors leading to cost over-run in highway projects [electronic resource] - Brisbane Queensland University of Technology 2005 - COBRA 2005 .

Discusses the influence of cost overrun risk factors in construction projects, and how these factors lead to control on project cost estimates and the identifying of solutions for avoiding future estimate overruns. Evaluates and reports on data on cost overruns from 238 completed design-bid-build highway projects each costing over $1m.

1741071011


AUSTRALIA