Rough justice for the subcontractor?
Knowles, R.
Rough justice for the subcontractor? - 1994 - CSM (Chartered Surveyor Monthly) 3(11) September 1994 44(1) .
Discusses "Erith Contractors Ltd v Costain Civil Engineering" 1993 concerning interpretation of arbitration clauses in the FCEC blue form of subcontract and the position of the subcontractor.
ARBITRATION CLAUSES
FCEC FORM OF SUBCONTRACT
SUBCONTRACTORS
SUBCONTRACTS
Rough justice for the subcontractor? - 1994 - CSM (Chartered Surveyor Monthly) 3(11) September 1994 44(1) .
Discusses "Erith Contractors Ltd v Costain Civil Engineering" 1993 concerning interpretation of arbitration clauses in the FCEC blue form of subcontract and the position of the subcontractor.
ARBITRATION CLAUSES
FCEC FORM OF SUBCONTRACT
SUBCONTRACTORS
SUBCONTRACTS