Quantifying disruption costs
Cree, C.
Quantifying disruption costs - Construction Law Journal 5(4) 258-262(5) .
Describes the process of quantifying disruption costs according to points made in Crosby Ltd v Portland UDC (1967), namely additional costs to individual disrupting events are not allocated and the contractor must give information for checking by the recipient of claims .
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
Quantifying disruption costs - Construction Law Journal 5(4) 258-262(5) .
Describes the process of quantifying disruption costs according to points made in Crosby Ltd v Portland UDC (1967), namely additional costs to individual disrupting events are not allocated and the contractor must give information for checking by the recipient of claims .
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS