Who should pay for site programme changes?

Bingham, T.

Who should pay for site programme changes? - 1990 - Building 255(7631) 19 January 1990, 41(1) .

Discusses the problem of juggling contracts and the position of subcontractors when projects are subject to delay or disruption . The case of Kitsons Sheet Metal Ltd and Kitsons Insulation Contractors v Matthew Hall Mechanical and Electrical Engineers , is used as an example.


BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
CLAIMS
SITE INSTRUCTIONS