Building agreement - 1990 - EGCS (1990) 48 .

In Underground (Civil Engineering) Ltd v Croydon LBC ChD 6 April 1990 it was held that clause (6)(a) of a building agreement under which it was agreed that if a workshop building and ancillary offices were not completed and fit for occupation within the time limit specified the council would take possession , was a forfeiture provision.