1990 Cambridge Lecture : GC/Works/1 Edition 3
Booth, S.
1990 Cambridge Lecture : GC/Works/1 Edition 3 - 1990 - Civil Engineering Surveyor 15(9) November 1990, 5-6(2) .
Discusses edition 3 of GC/Works/1 Conditions of contract. Key amendments include design liability , extension of time no longer allowed for weather conditions , the role of the project manager and the importance of progress meetings .
MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION
PSA
VARIATION INSTRUCTIONS
1990 Cambridge Lecture : GC/Works/1 Edition 3 - 1990 - Civil Engineering Surveyor 15(9) November 1990, 5-6(2) .
Discusses edition 3 of GC/Works/1 Conditions of contract. Key amendments include design liability , extension of time no longer allowed for weather conditions , the role of the project manager and the importance of progress meetings .
MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION
PSA