Contractor and subcontractor must agree
Powell-Smith, V.
Contractor and subcontractor must agree - 1987 - Contract Journal 5 March 1987, 7(1) .
Highlights difficulties which can arise regarding subcontract claims in respect of delay and disruption under the JCT forms of building contract .
JCT STANDARD FORM OF BUILDING CONTRACT (1980 EDITION)
NSC 4
Contractor and subcontractor must agree - 1987 - Contract Journal 5 March 1987, 7(1) .
Highlights difficulties which can arise regarding subcontract claims in respect of delay and disruption under the JCT forms of building contract .
JCT STANDARD FORM OF BUILDING CONTRACT (1980 EDITION)
NSC 4