Architect must tot up contractor`s losses
Powell-Smith, V.
Architect must tot up contractor`s losses - 1992 - Contract Journal 364(5884) 30 July 1992, 7(1) .
Examines clause 26.1 of JCT 80 and the architect`s involvement in the procedure to be followed for claiming reimbursement of direct loss and expense on behalf of the contractor.
ARCHITECTS
CONTRACT CLAIMS
CROUDACE LTD V LAMBETH BC
LOSS AND EXPENSE
MERTON LBC V STANLEY HUGH LEACH LTD
REIMBURSEMENT
Architect must tot up contractor`s losses - 1992 - Contract Journal 364(5884) 30 July 1992, 7(1) .
Examines clause 26.1 of JCT 80 and the architect`s involvement in the procedure to be followed for claiming reimbursement of direct loss and expense on behalf of the contractor.
ARCHITECTS
CONTRACT CLAIMS
CROUDACE LTD V LAMBETH BC
LOSS AND EXPENSE
MERTON LBC V STANLEY HUGH LEACH LTD
REIMBURSEMENT