Late completion
Late completion
- 1987
- Times 22/8/87 p33 .
It was held in Temloc Ltd v Errill Properties Ltd CA 29 July 1987 that the employers, Errill Properties, were not entitled to damages for late completion from the contractors, Temloc Ltd.
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
JCT 80
LIQUIDATED DAMAGES
It was held in Temloc Ltd v Errill Properties Ltd CA 29 July 1987 that the employers, Errill Properties, were not entitled to damages for late completion from the contractors, Temloc Ltd.
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
JCT 80
LIQUIDATED DAMAGES