Blaenau Gwent BC v Lock

Blaenau Gwent BC v Lock - 1994 - Construction Industry Law Letter (1994) CILL 904-905(2) .

19 January 1994. A series of payments for fluctuations was made to contractors under ICE conditions 5th edition Cl 60(6). After the 23rd payment the engineer accepted the contractors` revised calculations and the contractors increased their claims on the grounds that the earlier claims had been incorrect. The arbitrator subsequently agreed and awarded interest on the excess due to the contractors. This award was disputed by B on the grounds that the interest was not claimed when it became due. The decision in "SoS Transport v Birse-Farr Joint Venture" 1993 followed.


CIVIL ENGINERRING CONTRACTS
CLAIMS
ICE CONDITIONS OF CONTRACT 5TH EDITION CL60(6)
INTEREST