Constraints on additional payments
Dodd, O.
Constraints on additional payments - 1987 - Contract Journal 338(5625) 6 August 1987, 9(1) .
This article investigates whether claims for further payment including increased cost of labour and material would succeed under JCT 1980 , if clauses 4.6 and 4.5 were deleted from the Minor Works Form .
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS
Constraints on additional payments - 1987 - Contract Journal 338(5625) 6 August 1987, 9(1) .
This article investigates whether claims for further payment including increased cost of labour and material would succeed under JCT 1980 , if clauses 4.6 and 4.5 were deleted from the Minor Works Form .
BUILT ENVIRONMENT-BUILDING CONTRACT FORMS