Harbour & General Works Ltd v Environment Agency
- 1999
- Construction Industry Law Letter [1999] CILL 1556-1559 .
CA 12 October 1999. Extension of time in which to commence arbitration under Arbitration Act 1996 s12. 'Final & binding' under ICE conditions of contract, clause 66. ICE Arbitration procedure, rule 5.2. (Taken from journal headnote)
HARBOUR AND GENERAL WORKS LTD V ENVIRONMENT AGENCY
ARBITRATION ACT 1996 S12
ICE CONDITIONS OF CONTRACT 5TH EDITION CL66
ICE ARBITRATION PROCEDURE
TIME LIMITS
CA 12 October 1999. Extension of time in which to commence arbitration under Arbitration Act 1996 s12. 'Final & binding' under ICE conditions of contract, clause 66. ICE Arbitration procedure, rule 5.2. (Taken from journal headnote)