Gives details of lead times for various products including piling, concrete works, structural steel frames, precast concrete frames, cladding and roofing. Notes that the big changes anticipated at the end of last year have failed to materialise as lead times remain steady. Includes a feature on curtain walling, with graphs showing lead times, order levels and tender prices.
Lead times - 2005 - Building 270(8375) 1 April 2005, 62-65(4) .
Gives details of lead times for various products including piling, concrete works, structural steel frames, precast concrete frames, cladding and roofing. Notes that the big changes anticipated at the end of last year have failed to materialise as lead times remain steady. Includes a feature on curtain walling, with graphs showing lead times, order levels and tender prices.