The Dorchester Hotel Limited v Vivid Interiors Limited (Record no. 81300)

MARC details
000 -LEADER
fixed length control field 02185cad a22002175a 4500
001 - CONTROL NUMBER
control field L146824
008 - FIXED-LENGTH DATA ELEMENTS--GENERAL INFORMATION
fixed length control field 090303e20090119xxk f v 000 0 eng d
035 ## - SYSTEM CONTROL NUMBER
System control number (Sirsi) u146824
041 0# - LANGUAGE CODE
Language code of text/sound track or separate title eng
245 04 - TITLE STATEMENT
Title The Dorchester Hotel Limited v Vivid Interiors Limited
Medium [electronic resource]
260 ## - PUBLICATION, DISTRIBUTION, ETC.
Date of publication, distribution, etc. 2009
520 ## - SUMMARY, ETC.
Summary, etc. [2009] EWHC 70 (TCC), 19 January 2009. The case considers a dispute over a final account claim, a complaint of an adjudication timetable too short to allow proper examination of documentation and the possibility of a breach of natural justice. The Dorchester Hotel Ltd (D) contracted with Vivid Interiors Ltd (V) for refurbishment works. Once works completed, V sent its final account to D. In December 2008, V commenced adjudication proceedings in respect with payment for his works. The date of the end of adjudication was extended to 28 February 2009. As documentation, V gave a referral notice with 37 arch files. V also produced a different final account than the previous one. D argued that the timetable was too tight to examine the new evidence and the revised figures, and that there was a risk of natural breach of justice. V argued that the court had no jurisdiction to intervene in an ongoing adjudication. "Held": The court has jurisdiction to intervene, particularly if there has been or will be a breach of natural justice. However, this should be done in exceptional cases. The judge could not at this stage state that there would be a breach of natural justice. The timetable could still reach a fair result. The claimant could still use his claim of breach of natural justice in the future if unhappy with adjudicator's decision.
590 ## - LOCAL NOTE (RLIN)
Local note KA
650 24 - SUBJECT ADDED ENTRY--TOPICAL TERM
Topical term or geographic name entry element DORCHESTER HOTEL LIMITED V VIVID INTERIORS LIMITED
650 24 - SUBJECT ADDED ENTRY--TOPICAL TERM
Topical term or geographic name entry element VITPOL BUILDING SERVICE V SAMEN
650 24 - SUBJECT ADDED ENTRY--TOPICAL TERM
Topical term or geographic name entry element CJP BUILDERS LIMITED V WILLIAM VERRY LIMITED
651 #4 - SUBJECT ADDED ENTRY--GEOGRAPHIC NAME
Geographic name England and Wales
Chronological subdivision 1543-
690 ## - LOCAL SUBJECT ADDED ENTRY--TOPICAL TERM (OCLC, RLIN)
Topical term or geographic name as entry element MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
856 40 - ELECTRONIC LOCATION AND ACCESS
Uniform Resource Identifier <a href="https://www.bailii.org/ew/cases/EWHC/TCC/2009/70.html ">https://www.bailii.org/ew/cases/EWHC/TCC/2009/70.html </a>
Public note View the case free of charge at www.bailli.org...
942 ## - ADDED ENTRY ELEMENTS (KOHA)
Suppress in OPAC 0
Holdings
Withdrawn status Lost status Source of classification or shelving scheme Damaged status Not for loan Home library Current library Shelving location Date acquired Total Checkouts Full call number Barcode Date last seen Copy number Price effective from Koha item type
    Dewey Decimal Classification     Virtual Virtual Online 03/03/2009   ONLINE JUDGMENT 146824-2001 06/08/2019 1 06/08/2019 Law report