Construction Group Centre Ltd v Highland Council
Series: Building Law Reports ; [2002] 10 BLR 476-488(13)Publication details: 2002Subject(s):- MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION-ADJUDICATION AWARDS
- MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION-ADJUDICATION AWARDS
- CONSTRUCTION CENTRE GROUP LTD V HIGHLAND COUNCIL
- CONSTRUCTION DISPUTES
- DAVID MCLEAN HOUSING CONTRACTORS LTD V SWANSEA HOUSING ASSOCIATION LTD
- K N S INDUSTRIAL SERVICES (BIRMINGHAM) LTD V SINDALL LTD
- LIQUIDATED DAMAGES
- SOLLAND INTERNATIONAL LTD V DARAYDAN HOLDINGS LTD
- MANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION
| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Law report | London Journal article | X12136 (Browse shelf(Opens below)) | 1 | Available | 121437-1001 |
CSOH 23 August 2002. The pursuers (C) brought proceedings for payment of an adjudicator's award, which the defenders (H) contended on the grounds that: the award was provisional, and the contract's arbitration provisions would not allow the arbiter to take into account a final Court decree in accordance with the adjudicator's decision; they had a larger claim against C for the payment of liquidate damages. "Held": C was required by the contract to implement the adjudicator's decision regardless of whether it was right or wrong; if the decree was granted the arbiter could still award C less than had been paid under that decree; H had lost their right of retention as they had not advanced it at the proper time during the course of the adjudication (see also Abs65934). View judgment at www.scotcourts.gov.uk.