Crown House Engineering Ltd v AMEC Projects

Language: English Series: Construction Industry Law Letter ; (1989) CILL 536-537(2)Publication details: 1989Subject(s): Summary: CA 30 November 1989. Crown (C) carried out M & E works for AMEC (A); interim certificates were issued, but there was doubt as to whether a contract was ever concluded between C and A. C began proceedings against A for payment, pleaded initially in contract but later amended for a reasonable sum as quantum meruit . C started a second action against A for retention monies . In the main action C applied for an 0.29 interim payment; in the retention action C sought 0.14 summary judgement. They were successful in both applications. A appealed against both orders. Both of A`s appeals allowed.
Holdings
Item type Current library Call number Copy number Status Barcode
Law report London Journal article ABS42126 (Browse shelf(Opens below)) 1 Available 34849-1001

CA 30 November 1989. Crown (C) carried out M & E works for AMEC (A); interim certificates were issued, but there was doubt as to whether a contract was ever concluded between C and A. C began proceedings against A for payment, pleaded initially in contract but later amended for a reasonable sum as quantum meruit . C started a second action against A for retention monies . In the main action C applied for an 0.29 interim payment; in the retention action C sought 0.14 summary judgement. They were successful in both applications. A appealed against both orders. Both of A`s appeals allowed.