Balfour Beatty Construction (Scotland) Limited v Scottish Power plc

Language: English Series: Scots Law Times ; 1994 SLT 807-811(5)Publication details: 1994Subject(s): Summary: House of Lords. 17 March 1994. Contract - Breach of contract - damages - remoteness of damage - reasonable foreseeability of loss - supply of electricity for construction contract - interruption of supply leading to requirement to demolosh and rebuild partly completed structure - whether foreseeable.

House of Lords. 17 March 1994. Contract - Breach of contract - damages - remoteness of damage - reasonable foreseeability of loss - supply of electricity for construction contract - interruption of supply leading to requirement to demolosh and rebuild partly completed structure - whether foreseeable.