Welsh Development Agency v Redpath Dorman Long Ltd

Language: English Series: Construction Law Journal ; (1994) 10 CLJ 325-336(12)Publication details: 1994Subject(s): Summary: CA 17 March 1994. W engaged R to design the sub-structure for factory units on a site at which the level had been raised by tipping. Starting in October 1980, 12 factory units were constructed pursuant to R`s recommendations that the buildings but not the floors should be piled. Two units were let to a tenant who subsequently complained the floors had settled. R investigated and issued a statement confirming the settling but that there would be no more. Settlement continued and the tenant had to be relocated. W issued a writ in 1990 and added amendments to the claim in 1992. Judgment allowed claims for breach of contract and for the remaining 10 units but did not allow a further claim against R for negligent misstatement.
Holdings
Item type Current library Call number Copy number Status Barcode
Law report London Journal article ABS51697 (Browse shelf(Opens below)) 1 Available 40391-1001

CA 17 March 1994. W engaged R to design the sub-structure for factory units on a site at which the level had been raised by tipping. Starting in October 1980, 12 factory units were constructed pursuant to R`s recommendations that the buildings but not the floors should be piled. Two units were let to a tenant who subsequently complained the floors had settled. R investigated and issued a statement confirming the settling but that there would be no more. Settlement continued and the tenant had to be relocated. W issued a writ in 1990 and added amendments to the claim in 1992. Judgment allowed claims for breach of contract and for the remaining 10 units but did not allow a further claim against R for negligent misstatement.