An increased burden on the employer
Language: English Series: Contract Journal ; 358 (5812) 14 March 1991, 8 (1)Publication details: 1991Subject(s): Summary: The ICE Conditions of contract 6th edition makes the employer responsible for making available to the contractor all information on the nature of the soil conditions obtained by the employer`s investigations. This represents a substantial change in the current common law position.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS44192 (Browse shelf(Opens below)) | 1 | Available | 45731-1001 |
The ICE Conditions of contract 6th edition makes the employer responsible for making available to the contractor all information on the nature of the soil conditions obtained by the employer`s investigations. This represents a substantial change in the current common law position.