Deduction for completion delay
Language: English Series: Independent ; 11 June 1993, 35(1)Publication details: 1993Subject(s): Summary: In "JF Finnegan ltd v Community Housing Association Ltd", ORC 4 June 1993, it was held that under JCT 1980 cl 24.2.1, which deals with liquidated and ascertained damages for delayed completion, the employer must make a requirement in writing of the contractor before making a deduction for liquidated damages.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Law report | London Journal article | WB2922-10 (Browse shelf(Opens below)) | 1 | Available | 48172-1001 |
In "JF Finnegan ltd v Community Housing Association Ltd", ORC 4 June 1993, it was held that under JCT 1980 cl 24.2.1, which deals with liquidated and ascertained damages for delayed completion, the employer must make a requirement in writing of the contractor before making a deduction for liquidated damages.