Contractual overruns and extensions of time

By: Language: English Series: Construction Law Journal ; 8(1) 1992, 32-40(5)Publication details: 1992Subject(s): Summary: Considers the ambiguity of the phrase `extension of time for completion` which can mean either `postponement of the date or the point in time by which completion of the contract work is to be expected` or `increase in the number of hours, days or weeks which are required to carry out the work in question`.

Considers the ambiguity of the phrase `extension of time for completion` which can mean either `postponement of the date or the point in time by which completion of the contract work is to be expected` or `increase in the number of hours, days or weeks which are required to carry out the work in question`.