Architect must grant extension

By: Language: English Series: Contract Journal ; 367(5923) 6 May 1993, 8-9(2)Publication details: 1993Subject(s): Summary: Discusses "Balfour Beatty v Chestermount Properties Ltd" (Abs48385) which examined whether, when a variation is ordered during a period of delay for which the contractor is responsible the extension of time consequent on the variation should start from the date the variation is ordered.

Discusses "Balfour Beatty v Chestermount Properties Ltd" (Abs48385) which examined whether, when a variation is ordered during a period of delay for which the contractor is responsible the extension of time consequent on the variation should start from the date the variation is ordered.