Contractors` escape route blocked up

By: Language: English Series: Building ; 258(22) 28 May 1993, 34-35(2)Publication details: 1993Subject(s): Summary: Summarises "Balfour Beatty Building v Chestermount Properties" (1993), on the issue of calculation of liquidated damages for delay by the contractor, when a variation has been issued after the completion date. The court decision did not allow contractors to avoid liquidated damages in these circumstances.

Summarises "Balfour Beatty Building v Chestermount Properties" (1993), on the issue of calculation of liquidated damages for delay by the contractor, when a variation has been issued after the completion date. The court decision did not allow contractors to avoid liquidated damages in these circumstances.