By: Language: English Series: Building ; 260(7882) 3 March 1995, 32-33(2)Publication details: 1995Subject(s): Summary: Reports on a year long dispute for payment and a counter claim for defective work and delay with the initial problem being whether to arbitrate or litigate. The work had been done on a letter of intent with reference to JCT Works Contract/2 but this was not held to give effect to the arbitration clause in that contract.

Reports on a year long dispute for payment and a counter claim for defective work and delay with the initial problem being whether to arbitrate or litigate. The work had been done on a letter of intent with reference to JCT Works Contract/2 but this was not held to give effect to the arbitration clause in that contract.