Image from Google Jackets

R v Dudley Magistrates` Court ex parte Hollis; Hollis v Dudley MBC; Probert v Dudley MBC

Language: English Series: Estates Gazette ; [1998] 18 EG 133-138(6)Publication details: 1998Subject(s): Summary: QBD 25 November 1997. H and P served notice on D of intention to bring proceedings against them if necessary remedial works were not carried out within 21 days to rectify a statutory nuisance. D promptly replied to say that the works would take longer than 21 days. Shortly after the expiry of this period, H and P commenced proceedings. Their costs were disallowed on the grounds that they had failed to give D proper opportunity to complete the works, and had acted unreasonably in their action. H and P`s appeal was allowed, and judicial review on adjournment of the case granted.
Holdings
Item type Current library Call number Copy number Status Barcode
Law report London Journal article ABS58792 (Browse shelf(Opens below)) 1 Available 86380-1001

QBD 25 November 1997. H and P served notice on D of intention to bring proceedings against them if necessary remedial works were not carried out within 21 days to rectify a statutory nuisance. D promptly replied to say that the works would take longer than 21 days. Shortly after the expiry of this period, H and P commenced proceedings. Their costs were disallowed on the grounds that they had failed to give D proper opportunity to complete the works, and had acted unreasonably in their action. H and P`s appeal was allowed, and judicial review on adjournment of the case granted.