Determination of completion date
Language: English Series: EGCS ; 1990 87Publication details: 1990Subject(s): Summary: Rosehaugh Stanhope (Broadgate Phase 6) plc and another v Redpath Dorman Long Ltd CA 26 June 1990. The appeal was allowed that with the contractor `s denial of the breach of contractual obligation to complete by specified dates and the construction manager`s inability to prove this, the construction manager `s determination of damage liability is not binding.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| News article | London News article | WB2627-04 (Browse shelf(Opens below)) | 1 | Available | 9369-1001 |
Rosehaugh Stanhope (Broadgate Phase 6) plc and another v Redpath Dorman Long Ltd CA 26 June 1990. The appeal was allowed that with the contractor `s denial of the breach of contractual obligation to complete by specified dates and the construction manager`s inability to prove this, the construction manager `s determination of damage liability is not binding.