No obligation
Language: English Series: Chartered Quantity Surveyor ; 10(2) October 1987, 7(1)Publication details: 1987Subject(s): Summary: Reviews the decision in Glenlion Construction v The Guiness Trust , ORC 28 July 1987, see Abstract 38052, in which a dispute arose out of an early completion programme in a building contract. It was held that the architect was under no obligation to comply with the programme. Also briefly comments on Temloc v Errill Properties , CA 29 July 1987, see WB2334-10, which considered the provisions of JCT 1980 cl. 24.2.1 concerning damages for late completion .| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS38246 (Browse shelf(Opens below)) | 1 | Available | 9500-1001 |
Reviews the decision in Glenlion Construction v The Guiness Trust , ORC 28 July 1987, see Abstract 38052, in which a dispute arose out of an early completion programme in a building contract. It was held that the architect was under no obligation to comply with the programme. Also briefly comments on Temloc v Errill Properties , CA 29 July 1987, see WB2334-10, which considered the provisions of JCT 1980 cl. 24.2.1 concerning damages for late completion .