Language: English Series: Construction Industry Law Letter ; 1994 CILL 912-915(4)Publication details: 1994Subject(s): Summary: CA 22 February 1994. T were the main contractors for the construction of a leisure complex. They engaged K as the sub-contractor for groundworks. K procured a bond from G for 10% of the sub-contract sum. During the course of the work K went into receivership and T took over completion of the work and made a claim under the bond. The ORC found that the amount of damage sustained by T exceeded the amount and gave summary judgement for the full amount of the bond. G appealed. It was held that the bond imposed upon G an independent obligation to pay the damages sustained by T from the failure of the subcontractors to carry out the work. The bond did not create a guarantee in the ordinary sense. G argued that the sum payable should take into account all set-off and cross claims between the parties however CA held that G should pay the amount of the damages which T asserts is correct.
Holdings
Item type Current library Call number Copy number Status Barcode
Law report London Journal article ABS50820 (Browse shelf(Opens below)) 1 Available 97523-1001

CA 22 February 1994. T were the main contractors for the construction of a leisure complex. They engaged K as the sub-contractor for groundworks. K procured a bond from G for 10% of the sub-contract sum. During the course of the work K went into receivership and T took over completion of the work and made a claim under the bond. The ORC found that the amount of damage sustained by T exceeded the amount and gave summary judgement for the full amount of the bond. G appealed. It was held that the bond imposed upon G an independent obligation to pay the damages sustained by T from the failure of the subcontractors to carry out the work. The bond did not create a guarantee in the ordinary sense. G argued that the sum payable should take into account all set-off and cross claims between the parties however CA held that G should pay the amount of the damages which T asserts is correct.