Sunk by your own float

By: Series: Building ; 265(8119) 14 January 2000, 53(1)Publication details: 2000Subject(s): Summary: Discusses the case of "Ascon Contracting v Alfred McAlpine Construction Isle of Man" which concerned the use of a float in the main-contract programme. In this case, Ascon claimed that it was entitled to the 5 week float within McAlpine's main contract programme and the judge agreed with them.
Holdings
Item type Current library Call number Copy number Status Barcode
Journal article London Journal article ABS61750 (Browse shelf(Opens below)) 1 Available 103837-1001

Discusses the case of "Ascon Contracting v Alfred McAlpine Construction Isle of Man" which concerned the use of a float in the main-contract programme. In this case, Ascon claimed that it was entitled to the 5 week float within McAlpine's main contract programme and the judge agreed with them.