Adjudication: all change
Series: Construction News ; (6678) 10 August 2000, 26(1)Publication details: 2000Subject(s):- MANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
- CONSTRUCTION DISPUTES
- SCHEME FOR CONSTRUCTION CONTRACTS
- BUILT ENVIRONMENT-BUILDING CONTRACT FORMS-STANDARD FORMS OF BUILDING CONTRACT-INSTITUTION OF CIVIL ENGINEERS CONTRACTS
- NEW ENGINEERING CONTRACT
- JOHN MOWLEM V HYDRA-TIGHT
- DISPUTE RESOLUTION
| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS62725 (Browse shelf(Opens below)) | 1 | Available | 107925-1001 |
Discusses the decision in "John Mowlem v Hydra-Tight", which will have implications on adjudications under all the ICE forms of contract. The key points raised were that Option Y of the NEC Engineering Contract doesn't comply with the Construction Act and that the ICE 7th Edition will also be affected and that a 'person' under Paragraph 2.1(a) of the Scheme may be identified in a list issued after the dispute arises.