Image from Google Jackets

Simply a question of 'right' interpretation

By: Series: Contract Journal ; 407(6315) 21 February 2001, 33(1)Publication details: 2001Subject(s): Summary: Examines various cases to determine which construction operations are exempt under the Construction Act 1996 s105(1). Concludes that when deciding if an activity is excluded by s105(1), both the activity and the whole site has to be included in the excluded definitions.

Examines various cases to determine which construction operations are exempt under the Construction Act 1996 s105(1). Concludes that when deciding if an activity is excluded by s105(1), both the activity and the whole site has to be included in the excluded definitions.