By: Series: Building ; 266(8182) 27 April 2001, 52-53(2)Publication details: 2001Subject(s): Summary: Considers the case of "Beechwood Development Company (Scotland) Ltd v Stuart Mitchell t/a Discovery Land Surveys" in which Beechwood, a housebuilder, was awarded £31,000 damages for losses incurred from a delayed start to a building contract. Argues that an adjudicator may have come to a different conclusion on the basis that Beechwood was only temporarily out of pocket, and the lost time could have been made up in the longer term.

Considers the case of "Beechwood Development Company (Scotland) Ltd v Stuart Mitchell t/a Discovery Land Surveys" in which Beechwood, a housebuilder, was awarded £31,000 damages for losses incurred from a delayed start to a building contract. Argues that an adjudicator may have come to a different conclusion on the basis that Beechwood was only temporarily out of pocket, and the lost time could have been made up in the longer term.