Co-operative Insurance Society Ltd v Henry Boot Scotland Ltd and others
Language: English Publication details: 2003Subject(s): Online resources: Summary: [2002] EWHC 1270 (TCC) 1 July 2002. Claimant (CIS) as employer claimed against main contractor (HB) and consulting engineer (CHW) for alleged breach of contractual obligations, under the to the JCT 80 Private with Quantities Contractors Designed Portion Supplement, after water and soil flooded sub-basement excavations. Although CHW produced a concept design for the substructure, earthwork, support and ground water exclusion, HB was held to be responsible for checking CHW's design. Due to a drafting error in the bills of quantities, HB was entitled to be paid for extra work under cl13.2 despite the design liability risk.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Law report | Virtual Online | ONLINE PUBLICATION (Browse shelf(Opens below)) | 1 | Available | 121239-2001 |
Browsing Virtual shelves, Shelving location: Online Close shelf browser (Hides shelf browser)
| No cover image available | No cover image available | No cover image available | No cover image available | No cover image available | No cover image available | No cover image available | ||
| ONLINE PUBLICATIOIN Spotlight [electronic resource] Housing and aging population | ONLINE PUBLICATION Heathrow night noise breaches human rights | ONLINE PUBLICATION Centralan Property Ltd v Customs and Excise Commissioners | ONLINE PUBLICATION Co-operative Insurance Society Ltd v Henry Boot Scotland Ltd and others | ONLINE PUBLICATION Sahib Foods Ltd v Paskin Kyriakides Sands [eletronic resource] | ONLINE PUBLICATION Satellite dishes and other antennas consultation on possible changes to planning regulations | ONLINE PUBLICATION Good business? |
[2002] EWHC 1270 (TCC) 1 July 2002. Claimant (CIS) as employer claimed against main contractor (HB) and consulting engineer (CHW) for alleged breach of contractual obligations, under the to the JCT 80 Private with Quantities Contractors Designed Portion Supplement, after water and soil flooded sub-basement excavations. Although CHW produced a concept design for the substructure, earthwork, support and ground water exclusion, HB was held to be responsible for checking CHW's design. Due to a drafting error in the bills of quantities, HB was entitled to be paid for extra work under cl13.2 despite the design liability risk.