PFI: construction performance

Series: National Audit Office Press Notice ; 5 February 2003 (3)Publication details: 2003Subject(s): Summary: The report by the National Audit Office on construction work carried out under the PFI generally found that the work was done on time and within the cost expected by the public sector. PFI provided a higher degree of price certainty, timely delivery and good quality built assets in comparison with previous conventional public sector building projects. NAO Press Notice http://www.nao.gov.uk/pn/02-03/0203371.htm

The report by the National Audit Office on construction work carried out under the PFI generally found that the work was done on time and within the cost expected by the public sector. PFI provided a higher degree of price certainty, timely delivery and good quality built assets in comparison with previous conventional public sector building projects. NAO Press Notice http://www.nao.gov.uk/pn/02-03/0203371.htm