Case news Bryen and Langley v Boston

By: Language: English Series: Property Week ; 70(35) 2 September 2005, 71(1)Publication details: 2005Subject(s): Summary: Discusses the case "Bryen and Langley Limited v Martin Boston" (L130784) which showed that even though a formal JCT building contract had not been signed, the dealings between the parties showed that they were contractually committed on the basis of the JCT contract and consequently the adjudicator did have jurisdiction to make an award in their dispute.
Holdings
Item type Current library Call number Copy number Status Barcode
Journal article London Journal article L130888 (Browse shelf(Opens below)) 1 Available 130888-1001

Discusses the case "Bryen and Langley Limited v Martin Boston" (L130784) which showed that even though a formal JCT building contract had not been signed, the dealings between the parties showed that they were contractually committed on the basis of the JCT contract and consequently the adjudicator did have jurisdiction to make an award in their dispute.