Melville Dundas Ltd (in receivership) v George Wimpey UK Ltd and another
Language: English Publication details: 2005Subject(s): Online resources: Summary: [2005] ScotCS CSIH 18, 15 December 2005. In March 2002, M entered into a design and build contract with W. M submitted an application for interim payment in May 2003, but before W had the opportunity to pay, M applied to be put into receivership. The issue was whether M was due its payment, as clause 27 of the contract appeared to prevent payment being made to an insolvent contractor. "Held" M was entitled to payment in full. The parties had intended the provisions of the Housing Grants, Construction and Regeneration Act 1996 s111 to apply, and had agreed the final date for payment as 14 days after application for payment had been submitted by M; application had been made on 2 May 2003, and therefore the final date for payment was indisputably 16 May. Clause 27 served only to terminate M's employment, and did not rescind the contract itself.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Law report | Virtual Online | ONLINE PUBLICATION (Browse shelf(Opens below)) | 1 | Available | 132696-1001 |
Browsing Virtual shelves, Shelving location: Online Close shelf browser (Hides shelf browser)
| No cover image available | No cover image available | No cover image available | No cover image available | No cover image available | No cover image available | No cover image available | ||
| ONLINE PUBLICATION How disruptive will HIPs be? | ONLINE PUBLICATION Formal request for casino bids | ONLINE PUBLICATION Castlebay Limited v Asquith Properties Limited | ONLINE PUBLICATION Melville Dundas Ltd (in receivership) v George Wimpey UK Ltd and another | ONLINE PUBLICATION New advice for employers on involving workers in health and safety management | ONLINE PUBLICATION HSE announces new timetable for construction design regulations | ONLINE PUBLICATION Employers urged to respond to high demand for construction apprenticeships |
[2005] ScotCS CSIH 18, 15 December 2005. In March 2002, M entered into a design and build contract with W. M submitted an application for interim payment in May 2003, but before W had the opportunity to pay, M applied to be put into receivership. The issue was whether M was due its payment, as clause 27 of the contract appeared to prevent payment being made to an insolvent contractor. "Held" M was entitled to payment in full. The parties had intended the provisions of the Housing Grants, Construction and Regeneration Act 1996 s111 to apply, and had agreed the final date for payment as 14 days after application for payment had been submitted by M; application had been made on 2 May 2003, and therefore the final date for payment was indisputably 16 May. Clause 27 served only to terminate M's employment, and did not rescind the contract itself.