Weather events

By: Language: English Series: Contract Journal ; 443(6680) 18 June 2008, 28-29(2)Publication details: 2008Subject(s): Summary: Looks at JCT and NEC conditions for adverse weather - under JCT weather must be exceptional and must adversely affect the works. Under NEC, however, a contractor must first establish: if there was an effect due to weather; whether it was sufficiently rare and if it amounts to a compensation event.

Looks at JCT and NEC conditions for adverse weather - under JCT weather must be exceptional and must adversely affect the works. Under NEC, however, a contractor must first establish: if there was an effect due to weather; whether it was sufficiently rare and if it amounts to a compensation event.