A question of perfect timing
Language: English Series: Building ; 259(7862) 30 September 1994, 30-31(2)Publication details: 1994Subject(s): Summary: Discusses "Pigott Foundations Ltd v Shepherd Construction Ltd" 1994 which found that a subcontractor under the terms of the standard form of subcontract DOM/1 is not liable for loss and expense if a delay in his schedule holds up the main contract.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | ABS51340 (Browse shelf(Opens below)) | 1 | Available | 22599-1001 |
Discusses "Pigott Foundations Ltd v Shepherd Construction Ltd" 1994 which found that a subcontractor under the terms of the standard form of subcontract DOM/1 is not liable for loss and expense if a delay in his schedule holds up the main contract.