| 245 | 4 | _aThe top ten lessons learned in construction contracting | |
| 260 | _c1996 | ||
| 350 | _a0 | ||
| 490 |
_aCost Engineering _v38(5) May 1996, 20-24(5) |
||
| 520 | _aThe results of research into construction contracting `trade secrets`. The interviews with ten categories of professionals in the construction industry revealed the following to be the top ten lessons learned: documentation, tried and tested contracts, an arbitration clause, a payment clause, dealing with reputable firms, a review of the contract, change orders and ethical conduct. | ||
| 650 | _aARBITRATION CLAUSES | ||
| 650 | _aCHANGE ORDERS | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aCONSTRUCTION INDUSTRY | ||
| 650 | _aCONTRACTORS | ||
| 650 | _aPAYMENT CLAUSES | ||
| 650 | _aPROFESSIONAL ETHICS | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||