| 100 | _aHemsley, A. | ||
| 245 | _aProving contractors` claims | ||
| 260 | _c1996 | ||
| 350 | _a0 | ||
| 490 |
_aBuilding _v261(7947) 28 June 1996, 31(1) |
||
| 520 | _aThe author uses case law to establish the level of detail required in construction contracts to protect parties if an extension of time is granted or when variations affect work on site. | ||
| 650 | _aBABCOCK ENERGY LTD V LODGE STURTEVANT LTD | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aBUILDING CONTRACTORS | ||
| 650 | _aEXTENSIONS OF TIME | ||
| 650 | _aTATE & LYLE FOOD DISTRIBUTION V GREATER LONDON COUNCIL | ||
| 650 | _aVARIATIONS | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||