245 _aProving contractors` claims
260 _c1996
350 _a0
490 _aBuilding
_v261(7947) 28 June 1996, 31(1)
520 _aThe author uses case law to establish the level of detail required in construction contracts to protect parties if an extension of time is granted or when variations affect work on site.
650 _aBABCOCK ENERGY LTD V LODGE STURTEVANT LTD
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aBUILDING CONTRACTORS
650 _aEXTENSIONS OF TIME
650 _aTATE & LYLE FOOD DISTRIBUTION V GREATER LONDON COUNCIL
650 _aVARIATIONS
690 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS