| 520 | _aExamines the decisions in two cases "Wharf Properties Ltd v Eric Cumine Associates" (ABS45395) and "Mid Glamorgan CC v Devonald Williams and Partners" (ABS45847) considering the implications on the way in which contractors prepare claims. | ||