| 100 | _aBrewer, G. | ||
| 245 | _aPayment provisions | ||
| 260 | _c2004 | ||
| 490 |
_aContract Journal _v424(6481) 23 June 2004, 22(1) |
||
| 520 | _aDiscusses "Alstom Signalling Ltd v Jarvis Facilities Ltd" ([2004] EWHC 1232 (TCC), [2004] All ER (D) 02 (Jun)), which concerned payment and withholding issues under cost reimburseable contracts. A subcontracted J to supply signalling equipment for a Railtrack project. Under the IChemE Model Form of Conditions of Contract for Process Plants, the subcontract stated J would be paid what the works cost, plus a management fee. When a dispute arose regarding the terms of the contract, J claimed it should be paid the entirity of what was due and the case went to adjudication. J was awarded an interim amount against A, but A appealed when dispute arose over the final amount. The claimant A sought a declaration regarding the terms of the subcontract with J and to recover a contribution to the total loss it claimed to have suffered under the main contract. "Held": J was not entitled to a summary judgment and the adjudicator's decision was set aside. Judgment available to view at www.bailii.org. | ||
| 590 | _aABS | ||
| 590 | _aABS | ||
| 650 | _aALSTOM SIGNALLING LTD V JARVIS FACILITIES LTD | ||
| 650 | _aCOST REIMBURSABLE CONTRACTS | ||
| 650 | _aICHEME MODEL FORM OF CONDITIONS OF CONTRACT FOR PROCESS PLANTS | ||
| 650 | _aADJUDICATION | ||
| 650 | _aBUILDING CONTRACTS | ||
| 650 | _aWITHHOLDING NOTICES | ||
| 690 |
_aDISPUTE RESOLUTION _96236 |
||
| 856 |
_uhttps://www.bailii.org/ew/cases/EWHC/TCC/2004/1285.html _zView judgment on the BAILII website... |
||