245 4 _aThe recovery of management costs
260 _c2004
490 _aContract Journal
_v425(6491) 2 September 2004, 26(1)
520 _aDiscusses "Euro Pools plc v Clydeside Steel Fabrications Ltd" (OHCS,unreported) which concerned whether a claimant may be entitled to recover management costs as a head of claim. E was engaged to install filtration systems for swimming pools and had subcontracted C to fabricate and supply the tanks. When, shortly after installation, the tanks started to suffer widespread corrosion, E claimed costs of remedial works from C, including time and travel costs of E's employees on the work and compensation for work they were unable to take on at this time. C argued no extra remuneration would have been earned, as staff just had to work harder. Judge found for E arguing that where employees are required to spend time on rectification works following a breach of contract, the employer will normally be entitled to recover the cost of the wages paid to those employees, together with a contribution to general overheads. View judgment at www.scotcourts.gov.uk.
590 _aABS
590 _aABS
650 _aEURO POOLS PLC V CLYDESIDE STEEL FABRICATIONS LTD
650 _aAMEC PROCESS AND ENERGY V STORK ENGINEERS AND CONTRACTORS
650 _aPHEE FARRER JONES V CONNAUGHT MASON
650 _aCLAIMS
650 _aMANAGEMENT COSTS
650 _aSUBCONTRACTORS
690 _aDISPUTE RESOLUTION-CASE LAW